UUFlexExecutive Cockpit

Programs & Integration 360

The program cockpit — turning status into an executable rollout plan across SAP S/4 + plant MES, Egypt / new-plant commissioning, the CPG account master & order-desk integration, and energy, yield & recycling, workstream by workstream, blocker by blocker, rupee by rupee.

UFlex Limited · FY26 (Mar'26, audited consolidated anchor)
India's largest multinational flexible-packaging & solutions company
12,000 employees · 14 plants & units · 9 plant countries
Executive read· the answer, then the moves

The program book is the value and the risk: ₹113 Cr of savings is still unbanked across 4 program-led businesses at 87% average modernization, with 8 open blockers gating the rollout — Egypt aseptic commissioning above all. Clear the critical path and bank the run-rate before FY27 volumes arrive.

4 of 4 headline metrics improving vs prior · still off target: Program Realization (Mix / Circularity / WC) 68.0% vs 100.0%, EBITDA Margin (Reported) 12.8% vs 15.0%, Overheads % of Income 8.6% vs 8.0%

Do now — ranked by urgency
  1. 1
    Clear the 8 open blockers on the critical pathAct now
    Why it matters

    Open blockers hold the rollout — and ₹113 Cr of unbanked savings — hostage across the 4 program-led businesses; the Egypt aseptic validation gates FY27 aseptic volumes outright.

    What's driving it
    • 8 blockers not yet resolved
    • 87% avg modernization across in-program
    • ₹14,022 Cr of revenue in program
    FYI
    • Blended cost-to-transform ROI 1.3x
    • Work the Blocker/High rows first
  2. 2
    Blocker: Egypt / New-Plant Commissioning — Asepto (Aseptic Liquid Packaging)Act now
    Why it matters

    Gates the program go-live (SAP S/4 ledger, plant MES & Egypt commissioning).

    What's driving it
    • due 2026-09-30 · Mitigating
    • Signal: Transformation blocker
    FYI
    • Egypt aseptic greenfield (USD 126 mn) final line validation & CPG qualification on the critical path — FY27 aseptic volumes gated on sign-off.
    • Owner: Transformation PMO
  3. 3
    Put a 90-day recovery plan on Working-capital & deleverageWatch
    Why it matters

    Working-capital & deleverage is leaking run-rate: ₹46 Cr actual vs ₹60 Cr plan (₹-14 Cr variance) — it compounds into the forecast quarters.

    What's driving it
    • Working-capital & deleverage variance ₹-14 Cr
    • Program total ₹369 Cr vs ₹405 Cr planned (₹-36 Cr)
    FYI

    Owner: Arun Kumar Sharma · Treasury

  4. 4
    Freeze discretionary spend on 90% PCR FilmWatch
    Why it matters

    90% PCR Film is underwater at 0.9x — ₹21 Cr spent against ₹18 Cr realized; halt discretionary spend until capture catches up.

    What's driving it
    • 90% PCR Film ROI 0.9x
    • Savings target ₹45 Cr vs realized ₹18 Cr
    FYI

    Protect the ≥1.3x businesses as the playbook

♻️ Specialty films & circularityStep 5 of 6 · commissioning & CPG qualificationValue-Added & Programs 360Deleverage & Re-ratingAll journeys
🌐 Enterprise 360 modules· on Programs & Integration 360Browse all 31 views ▾
● LiveBuilt forCIO · Digital / IT· what to roll out nextCFO· unbanked savingsBoard & Investors· the programs are the value & the risk

Faster program execution is one of UFlex's top priorities — it is where margin and savings are created and where they leak. This view turns "status" into an executable plan: the 4 program-led businesses (Asepto, Flex Films, Asclepius PCR, Flexible Packaging), their six workstreams (SAP S/4 + ledger, customer & CPG account master, order desk / CRM, plant MES / Industry-4.0, Egypt / new-plant commissioning, energy, yield & recycling), the blockers in the way, and the ~₹113 Cr of savings still unbanked waiting on the rollout.

Data backing: integration_workstream (6 workstreams × program business, % · owner · target) · integration_blocker (severity · owner · due) · integration_econ (budget · spend · savings) · synergy_track (program plan vs actual run-rate) · brand_cohort (modernization %, status)
Businesses in program
4
live workstream detail
Unbanked savings
₹113 Cr
target − realized
Avg modernization
87%
across in-program
Open blockers
8
not yet resolved
Cost-to-transform ROI
1.3x
savings ÷ spend
Revenue in program
₹14,022 Cr
4 businesses
Per-business program scorecard

Where each program-led business stands — and the next move

Do this: work the blocker named in each card first; if none, push the lowest-% workstream to its target date.

Flexible Packaging (Laminates & Pouches)
since 1988 · ₹3,389 Cr revenue · capture 84%
Integrated
Overall modernization95%
SAP S/4 / Ledger96%· Done
Customer & CPG Account Master78%· Sep 2026
Order Desk / CRM Integration84%· Aug 2026
Plant MES / Industry-4.080%· Sep 2026
Egypt / New-Plant Commissioning95%· Done
Energy, Yield & Recycling74%· Nov 2026
~180 duplicate CPG ship-to records across order desk & overseas entity ERPs await MDM steward merge before billing migration. · Data · MDM steward · due 2026-11-30
Next move: Clear the medium on Customer & CPG Account Master: ~180 duplicate CPG ship-to records across order desk & overseas entity ERPs await MDM steward merge before billing migration. (Data · MDM steward, due 2026-11-30).
Flex Films (Global Films)
since 1994 · ₹9,093 Cr revenue · capture 78%
Integrated
Overall modernization92%
SAP S/4 / Ledger78%· Sep 2026
Customer & CPG Account Master70%· Oct 2026
Order Desk / CRM Integration62%· Q4 2026
Plant MES / Industry-4.068%· Nov 2026
Egypt / New-Plant Commissioning88%· Aug 2026
Energy, Yield & Recycling72%· Dec 2026
Nigeria & UAE film lines not yet streaming OEE telemetry to the common MES; utilization gaps (66.7% / 65.7%) surface late. · Manufacturing · Ops · due 2026-11-15
Russia/CIS entity consolidation still runs on manual FX-translation workpapers (USD/INR closed 94.65); automation & controls pending. · Chief Information & Digital Officer · due 2026-10-30
Third-party PET-chip spot orders at Panipat quoted off-platform; pricing-governance gap vs SAP SD. · RevOps · Key CPG Accounts · due 2026-09-15
Dharwad BOPP construction telemetry to be wired into the MES backbone at commissioning (FY28). · Transformation PMO · due 2027-06-30
Next move: Clear the high on Plant MES / Industry-4.0: Nigeria & UAE film lines not yet streaming OEE telemetry to the common MES; utilization gaps (66.7% / 65.7%) surface late. (Manufacturing · Ops, due 2026-11-15).
Asepto (Aseptic Liquid Packaging)
since 2017 · ₹1,300 Cr revenue · capture 76%
In progress
Overall modernization88%
SAP S/4 / Ledger90%· Done
Customer & CPG Account Master82%· Aug 2026
Order Desk / CRM Integration78%· Sep 2026
Plant MES / Industry-4.086%· Done
Egypt / New-Plant Commissioning76%· Sep 2026
Energy, Yield & Recycling80%· Oct 2026
Egypt aseptic greenfield (USD 126 mn) final line validation & CPG qualification on the critical path — FY27 aseptic volumes gated on sign-off. · Transformation PMO · due 2026-09-30
Asepto liquor-carton artwork & state-excise approvals pending in two state markets. · President — Aseptic Liquid Packaging (Asepto) · due 2026-08-31
Next move: Clear the blocker on Egypt / New-Plant Commissioning: Egypt aseptic greenfield (USD 126 mn) final line validation & CPG qualification on the critical path — FY27 aseptic volumes gated on sign-off. (Transformation PMO, due 2026-09-30).
Asclepius (90% PCR Film)
since 2023 · ₹240 Cr revenue · capture 58%
In progress
Overall modernization72%
SAP S/4 / Ledger70%· Oct 2026
Customer & CPG Account Master64%· Nov 2026
Order Desk / CRM Integration55%· Dec 2026
Plant MES / Industry-4.066%· Oct 2026
Egypt / New-Plant Commissioning92%· Done
Energy, Yield & Recycling60%· Jan 2027
EPR recycled-content credit tracking is spreadsheet-based; audit trail needed for FY27 compliance filings. · Ops · Sustainability · due 2026-10-10
Next move: Clear the medium on Energy, Yield & Recycling: EPR recycled-content credit tracking is spreadsheet-based; audit trail needed for FY27 compliance filings. (Ops · Sustainability, due 2026-10-10).
Workstream heatmap

Six workstreams × program businesses

Read across each row for the business's weak spot; read down each column for the workstream that's stuck enterprise-wide. Tint = status; number = % complete.

BusinessSAP S/4 / LedgerCustomer & CPG Account MasterOrder Desk / CRM IntegrationPlant MES / Industry-4.0Egypt / New-Plant CommissioningEnergy, Yield & Recycling
Laminates & Pouches96%78%84%80%95%74%
Global Films78%70%62%68%88%72%
Aseptic Liquid Packaging90%82%78%86%76%80%
90% PCR Film70%64%55%66%92%60%
DoneOn trackAt riskBehind
Blocker & risk log

Everything in the way of a rollout, worst-first

Do this: assign each open blocker a named owner and a date; the Blocker/High rows are the ones holding savings hostage.

SeverityBusinessWorkstreamDescriptionOwnerDueStatus
BlockerAseptic Liquid PackagingEgypt / New-Plant CommissioningEgypt aseptic greenfield (USD 126 mn) final line validation & CPG qualification on the critical path — FY27 aseptic volumes gated on sign-off.Transformation PMO2026-09-30Mitigating
HighGlobal FilmsPlant MES / Industry-4.0Nigeria & UAE film lines not yet streaming OEE telemetry to the common MES; utilization gaps (66.7% / 65.7%) surface late.Manufacturing · Ops2026-11-15Open
HighGlobal FilmsSAP S/4 / LedgerRussia/CIS entity consolidation still runs on manual FX-translation workpapers (USD/INR closed 94.65); automation & controls pending.Chief Information & Digital Officer2026-10-30Open
MediumLaminates & PouchesCustomer & CPG Account Master~180 duplicate CPG ship-to records across order desk & overseas entity ERPs await MDM steward merge before billing migration.Data · MDM steward2026-11-30Open
Medium90% PCR FilmEnergy, Yield & RecyclingEPR recycled-content credit tracking is spreadsheet-based; audit trail needed for FY27 compliance filings.Ops · Sustainability2026-10-10Open
MediumGlobal FilmsOrder Desk / CRM IntegrationThird-party PET-chip spot orders at Panipat quoted off-platform; pricing-governance gap vs SAP SD.RevOps · Key CPG Accounts2026-09-15Open
LowAseptic Liquid PackagingOrder Desk / CRM IntegrationAsepto liquor-carton artwork & state-excise approvals pending in two state markets.President — Aseptic Liquid Packaging (Asepto)2026-08-31Mitigating
LowGlobal FilmsEgypt / New-Plant CommissioningDharwad BOPP construction telemetry to be wired into the MES backbone at commissioning (FY28).Transformation PMO2027-06-30Open
Savings realization vs plan

₹369 Cr realized vs ₹405 Cr planned · ₹-36 Cr variance

Do this: the negative-variance programs are leaking run-rate — put a 90-day recovery plan on each before they compound into the forecast quarters.

ProgramOwnerPlan ₹CrActual ₹CrVariance% captured
Value-added & specialty mix shift (Alox / high-barrier / PCR)Jeevaraj Pillai₹120 Cr₹112 Cr₹-8 Cr
93%
Aseptic scale-up & Egypt commissioningPresident — Aseptic Liquid Packaging (Asepto)₹85 Cr₹76 Cr₹-9 Cr
89%
Recycling / Project Plastic FixHead of Recycling & Circularity (Project Plastic Fix)₹45 Cr₹41 Cr₹-4 Cr
91%
Backward integration — PET chips (Panipat & Egypt)P.L. Sirsamkar₹95 Cr₹94 Cr₹-1 Cr
99%
Working-capital & deleverageArun Kumar Sharma · Treasury₹60 Cr₹46 Cr₹-14 Cr
77%
Program economics

Is it paying back? Blended 1.3x on cost-to-transform

Do this: protect the ≥1.3x businesses as the playbook; for sub-1x businesses, freeze discretionary program spend until savings capture catches up.

BusinessSinceBudgetSpentSavings targetSavings realizedROIStatus
90% PCR Film2023₹30 Cr₹21 Cr₹45 Cr₹18 Cr0.9xIn progress
Aseptic Liquid Packaging2017₹55 Cr₹42 Cr₹85 Cr₹52 Cr1.2xIn progress
Chemicals & Inks2004₹25 Cr₹19 Cr₹34 Cr₹22 Cr1.2xIn progress
UFlex Holography & Security1999₹20 Cr₹18 Cr₹30 Cr₹26 Cr1.4xIntegrated
UFlex Engineering & Cylinders1995₹18 Cr₹13 Cr₹24 Cr₹14 Cr1.1xIn progress
Global Films1994₹90 Cr₹74 Cr₹130 Cr₹92 Cr1.2xIn progress
Laminates & Pouches1988₹60 Cr₹55 Cr₹95 Cr₹80 Cr1.5xIntegrated